AI data centers turn to retired jet engines for power
What happened
TechCrunch reported on November 4, citing The New York Times, that some AI data centers are converting retired aircraft jet engines into natural-gas generators to skip years of waiting for grid connections and new turbines. xAI has installed eight converted units in Mississippi to power its Colossus 2 data center in Memphis. Analysts say such units can get a data center running within 24 months, while 100 MW of grid capacity in Northern Virginia takes about seven years.
Written by AI from the coverage · updated 2 hours ago
Coverage
Follow the reports to see the story from different sides.
- TechCrunch · AIData centers are turning to old jet engines as the wait for power grows
部分 AI 数据中心正将退役飞机的喷气发动机改装为天然气发电设备,以绕过电网接入和新涡轮机供应的多年等待。据《纽约时报》报道,xAI 已在密西西比州安装八台改装机组,为孟菲斯的 Colossus 2 数据中心供电;分析师称这类机组可让数据中心在 24 个月内运行,而北弗吉尼亚接入 100 megawatts 电网容量约需七年。
Heat over time
Heat now 9·Comparable peak 10(Nov 4 07:00)·Comparable change over 24 hours –
The trend only compares accounts observed without gaps, so its range may be smaller than the current heat. Hover or tap the chart for each hour; the left and right arrow keys step through it.