After GPUs, AI companies are racing for power-on dates

Nvidia and Amazon both bet on Texas power in the same week—Nvidia investing up to $3B in grid developer Lancium, Amazon building a 5,000 MW on-site gas plant in Pecos County. Chips are arriving, but transformer lead times exceed 128 weeks, and only 8.9 GW of 474 GW in Texas load applications have been approved. The power-on date is becoming a tighter bottleneck than GPUs.

Why it matters: Nvidia plans a $2B stake in grid developer Lancium while Amazon builds its own 5,000 MW gas plant in Texas, both skipping the public grid queue to lock in power earlier.